1. Question Content...
EXPLANATION
Answer: X - EXPLANATION Content.
Question1: What is the flag used for WBS elements for which you want to plan costs?Please choose the correct answer.Response:
Question2: Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?There are 3 correct answers to this question.Response:
Question3: When using budgeting and active availability control, which business transactions affect the current budget?There are 3 correct answers to this question.Response:
Question4: Which of the following items can be included in the planned costs for an activity besides the cost of the activity?There are 3 correct answers to this question.Response:
Question5: What are the various elements that are included in checking rules?There are 3 correct answers to this question.Response:
Question6: Which types of networks store all the activity and material component costs at the network header level and behave in the same way as all other order categories?Please choose the correct answer.Response:
Question7: The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following?There are 2 correct answers to this question.Response:
Question8: Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element?Please choose the correct answer.Response:
Question9: In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?Please choose the correct answer.Response:
Question10: In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?Please choose the correct answer.Response:
Question11: When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?There are 2 correct answers to this question.Response:
Question12: Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project?Please choose the correct answer.Response:
Question13: What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?Please choose the correct answer.Response:
Question14: If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.There are 2 correct answers to this question.Response:
Question15: Which of the following determines the item category assigned in the sales documents?There are 2 correct answers to this question.Response:
Question16: What are the prerequisites for automatic requirements grouping on the top WBS element of a project?There are 2 correct answers to this question.Response:
Question17: In which type of billing the total value to be billed is apportioned to individual dates in the billing plan according to defined rules?Please choose the correct answer.Response:
Question18: Could a user with Access Control List (ACL) authorization 'Read' lock a project?Please choose the correct answer.Response:
Question19: How are various stock types managed for each material component?Please choose the correct answer.Response:
Question20: When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?There are 2 correct answers to this question.Response:
Question21: You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?Please choose the correct answer.Response:
Question22: Which of the following can be derived automatically when you carry out scheduling in projects with networks?There are 2 correct answers to this question.Response:
Question23: Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?Please choose the correct answer.Response:
Question24: What is the procurement element for requirements planning?Please choose the correct answer.Response:
Question25: What do you choose when creating a new network by copying an operative network?There are 3 correct answers to this question.Response:
Question26: Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?Please choose the correct answer.Response:
Question27: Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?Please choose the correct answer.Response:
Question28: Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for WBS element WBS 2.You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.Which type of reporting allows you to achieve this?Please choose the correct answer.Response:
Question29: Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities?Please choose the correct answer.Response:
Question30: Which parameters determine if the network header or network activities are cost objects?There are 2 correct answers to this question.Response:
Question31: Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?Please choose the correct answer.Response:
Question32: Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?There are 3 correct answers to this question.Response:
Question33: Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?There are 2 correct answers to this question.Response:
Question34: In which type of project stock G/L account determination for project stock is controlled differently from collective stock using specific valuation classes for sales order stock and project stock in the material master?There are 2 correct answers to this question.Response:
Question35: Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.In this scenario planned costs are determined for which of the following?There are 3 correct answers to this question.Response:
Question36: Which function allows you to check consistency of the dates within the project structure with or without taking activities into account?Please choose the correct answer.Response:
Question37: Which account assignment category is important for non-valuated project stock with WBS and sales order item?Please choose the correct answer.Response:
Question38: Which statements about project coding mask are true?There are 3 correct answers to this question.Response:
Question39: Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?Please choose the correct answer.Response:
Question40: Which of the following information regarding cost activity is not relevant for the calculation of planned costs?Please choose the correct answer.Response:
Question41: An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?Please choose the correct answer.Response:
Question42: While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?Please choose the correct answer.Response:
Question43: Which of the following levels can you assign persons to work centers?There are 2 correct answers to this question.Response:
Question44: How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?Please choose the correct answer.Response:
Question45: What is the starting point for milestone billing?Please choose the correct answer.Response:
Question46: How do you optimize cash flows to maximize project profits and reduce project costs?Please choose the correct answer.Response:
Question47: Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project.Which of the following can be assigned?There are 3 correct answers to this question.Response:
Question48: Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?Please choose the correct answer.Response:
Question49: A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?There are 2 correct answers to this question.Response:
Question50: You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.Which of the following business processes can be mapped in Sales and Distribution?There are 3 correct answers to this question.Response:
Question51: What are the three areas of the project screen?There are 3 correct answers to this question.Response:
Question52: In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this information?Please choose the correct answer.Response:
Question53: Which of the following can be used to calculate and update interest in SAP project system?There are 2 correct answers to this question.Response:
Question54: In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?Please choose the correct answer.Response: